NASA Says Working With Partners on Artemis III, IV, V Moon Missions Despite Artemis I Delay

Artemis is one of the most ambitious programmes of NASA and aims to take humans back to the Moon.

NASA Says Working With Partners on Artemis III, IV, V Moon Missions Despite Artemis I Delay

Photo Credit: NASA

Casting and assembly of solid rocket booster for the Artemis IV mission

Highlights
  • NASA says "great progress" has been made on Artemis II mission
  • Artemis I has been delayed several times
  • Artemis I is now expected to be launched in March or April 2022
Advertisement

While the Artemis I is yet to take off, NASA and its partners across the US are already working on the Space Launch System (SLS) rocket for the second Artemis launch, which will be the first crewed Artemis mission. NASA said the teams of scientists working on the SLS rocket have made “great progress” in building it for the second Artemis mission. The teams are also testing major parts of the Artemis missions which are in pipeline for launch after the first two, the space agency added.

Artemis is one of the most ambitious programmes of NASA and aims to land humans on the Moon, the first time since the 1970s. NASA aims to reestablish humanity's lunar presence for a longer duration and turn the Moon into a launchpad for going to Mars. And Artemis I is the first in a series of increasingly complex missions under the programme. When ready, the SLS rocket will be the most powerful rocket in the world and because of its unprecedented capabilities, it will be able to send missions farther and faster.

Having two solid rocket boosters and four RS-25 engines, SLS produces more than 8.8 million pounds of thrust to launch each Artemis mission beyond Earth's orbit and onward to the Moon. More than 1,000 different companies across the US helped build the Artemis I SLS rocket and the SLS rockets that will launch future missions, NASA said in a blog post.

“The Space Launch System team is not just building one rocket but manufacturing several rockets for exploration missions and future SLS flights beyond the initial Artemis launch,” SLS programme manager John Honeycutt said.

NASA has planned Artemis I as an exploration-only mission. The spacecraft will travel 280,000 miles from Earth, thousands of miles beyond the Moon over four-to-six weeks. However, the launch has been repeatedly hit by delays. NASA initially planned to launch Artemis I in November last year, but then postponed it to February this year and now it is expected to launch in March or April.


Xiaomi India speaks exclusively to Orbital, the Gadgets 360 podcast, on their plans for 2022 and pushing for 120W fast charging with the 11i HyperCharge. Orbital is available on Spotify, Gaana, JioSaavn, Google Podcasts, Apple Podcasts, Amazon Music and wherever you get your podcasts.
Affiliate links may be automatically generated - see our ethics statement for details.
Comments

For the latest tech news and reviews, follow Gadgets 360 on X, Facebook, WhatsApp, Threads and Google News. For the latest videos on gadgets and tech, subscribe to our YouTube channel. If you want to know everything about top influencers, follow our in-house Who'sThat360 on Instagram and YouTube.

YouTube Lets Its Platform Be 'Weaponised' to Spread Misinformation, Fact Checkers Claim
iOS 15.2.1, iPadOS 15.2.1 Released to Fix HomeKit Denial-of-Service Vulnerability
Share on Facebook Gadgets360 Twitter Share Tweet Snapchat Share Reddit Comment google-newsGoogle News
 
 

Advertisement

Follow Us

Advertisement

© Copyright Red Pixels Ventures Limited 2024. All rights reserved.
Trending Products »
Latest Tech News »